What does “Time Spent” do?
This feature is designed as a timer, which allows you to monitor the minutes/hours spent on each task. It can be set by any task assignee or set in advance by project admins.
How to set “Time Spent”:
1 - Open the task to access its properties.
2 - You will find the “Time Spent” option
3 - Click on the "+" icon to record the productivity of the selected task and click Start Recording.
4 - Click on the "+" icon to stop recording the productivity of the selected task and click Stop.
Where to locate the “Time Spent Duration”:
1 - Open the project where you need to see the total time spent on the tasks.
2 - At the bottom left of the screen, you will see this information.
3 - Click on the data, a member list will appear. You will also have the option to delete the data or export them (Time Spent will show in the CSV report).